- In re Continental Engineering Corporation (GST AAR Telangana)
- 1. Unpaid amounts including escalation of price for works executed in pre-GST period:
- 2. Refund of excess deductions made:
- 3. Interest on delayed payments of interim payment certificates:
- 4. Cost of Arbitration:
- 5. Liquidated damages:
- 6. Interest on Arbitration Amount: